Red Rock Recreation Centre Rehabilitation
Federal contribution
$720,096
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 13, 2021
20212022202320242025
Built
Approved 6 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of Red Rock
- Construction start
- Oct 2, 2023(actual)
- Construction end
- Sep 30, 2025(actual)
Against the original forecast
- Construction end3 months earlyforecast Dec 19, 2025
Also in Red Rock
- Red Rock Water Pollution Control Plant$7.6M
- Replacement and Rehabilitation of Newton Avenue, Brompton Road and Stadler Avenue Water and Wastewater Infrastructure$1.1M
- Improvements to Red Rock Recreation Centre$271.8K
- Installation of Water Meters$82.5K
- Recreation Center Arena Roof Retrofit and Repair$80.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58196 in the federal list. How to read these figures.