Replacement and Rehabilitation of Newton Avenue, Brompton Road and Stadler Avenue Water and Wastewater Infrastructure
Federal contribution
$1.1M
$1,122,000
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2021
202120222023
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of Red Rock
- Construction start
- May 24, 2022(actual)
- Construction end
- Oct 10, 2023(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 20, 2022
- Construction end4 months earlyforecast Jan 31, 2024
Also in Red Rock