Upgrade of the Leamington Pollution Control Centre - Phases 4 and 5
Federal contribution
$6.0M
$6,000,000
Federal share33%
of $18.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Leamington
- Construction start
- Apr 20, 2009(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction end6 months lateforecast Apr 1, 2011
Also in Leamington
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23202 in the federal list. How to read these figures.