Pelee Drive Bevel Line Sanitary Sewer Collection
Federal contribution
$2.0M
$2,000,000
Federal share25%
of $8.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2015
2016201720182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Leamington
- Construction start
- Aug 10, 2016(actual)
- Construction end
- May 9, 2019(actual)
Against the original forecast
- Construction start12 months lateforecast Aug 10, 2015
- Construction end4 months earlyforecast Sep 13, 2019