Pelee Drive Bevel Line Sanitary Sewer Collection

Leamington, Ontario

completeWastewaterSCF
Federal contribution
$2.0M
$2,000,000
Federal share25%

of $8.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2015
2016201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Leamington
Construction start
Aug 10, 2016(actual)
Construction end
May 9, 2019(actual)

Against the original forecast

  • Construction start12 months lateforecast Aug 10, 2015
  • Construction end4 months earlyforecast Sep 13, 2019