New Administration Building

Leamington, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$3.5M
$3,471,612
Federal share28%

of $12.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of Leamington
Construction start
Jul 1, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start9 months earlyforecast Mar 21, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011