Replacement of the Village of Merrickville-Wolford Sewage Treatment Plant
Federal contribution
$2.2M
$2,249,573
Federal share33%
of $6.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Merrickville-Wolford
- Construction start
- May 15, 2010(actual)
- Construction end
- Mar 31, 2013(actual)
Against the original forecast
- Construction start14 months lateforecast Mar 1, 2009
- Construction end19 months lateforecast Aug 20, 2011
Also in Merrickville-Wolford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24544 in the federal list. How to read these figures.