Community Centre Upgrades
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022202320242025
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Merrickville-Wolford
- Construction start
- May 12, 2023(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction end15 months earlyforecast Mar 31, 2026
Also in Merrickville-Wolford
- Replacement of the Village of Merrickville-Wolford Sewage Treatment Plant$2.2M
- Main Street Watermain Replacement$319.3K
- Snowdons Corners Road Construction$139.3K
- Collar Hill Road Construction$91.7K
- Integrate and upgrade the communication and data management systems at the water and wastewater plants.$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60961 in the federal list. How to read these figures.