Snowdons Corners Road Construction
Federal contribution
$139,333
Federal share33%
of $418.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Merrickville-Wolford
- Construction start
- Sep 15, 2009(actual)
- Construction end
- Jul 15, 2010(actual)
Against the original forecast
- Construction start6 months earlyforecast Mar 31, 2010
- Construction end2 weeks lateforecast Jun 30, 2010