Back to projects

Replacement of Water Lines on Gore Street

Gore Bay, Ontario

completeDrinking WaterCC
Federal contribution
$324,441
Federal share33%

of $973.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Gore Bay
Construction start
Jun 1, 2009(actual)
Construction end
Apr 30, 2010(actual)

Also in Gore Bay