Construction of New Fire Hall

Gore Bay, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$113,333
Federal share33%

of $340.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Gore Bay
Construction start
Jul 1, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction end3 months earlyforecast Sep 30, 2011