Construction of Meldrum Bay Waterfront Exhibit Centre

Gore Bay, Ontario

completeTourismCC Top Up
Federal contribution
$175,918
Federal share25%

of $703.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jul 5, 2010(actual)
Construction end
Jun 12, 2011(actual)

Against the original forecast

  • Construction end5 months earlyforecast Oct 31, 2011

Also in Gore Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28111 in the federal list. How to read these figures.