Improvements to the Fourth Avenue Sewer

Aylmer, Ontario

completeWastewaterCC
Federal contribution
$257,656
Federal share33%

of $773.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Aylmer
Construction start
May 3, 2010(actual)
Construction end
Aug 30, 2010(actual)