Sanitary Sewer Crossings Reconstruction
Federal contribution
$166,665
Federal share33%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedJan 4, 2010
20102011
Built
Approved 7 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Aylmer
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast Sep 1, 2010