Sanitary Sewer Crossings Reconstruction

Aylmer, Ontario

completeWastewaterISF
Federal contribution
$166,665
Federal share33%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedJan 4, 2010
20102011
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Aylmer
Construction start
Oct 18, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 1, 2010

Also in Aylmer

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31620 in the federal list. How to read these figures.