Aylmer Smart Water Meter Upgrade

Aylmer, Ontario

completeDrinking WaterCWWF
Federal contribution
$407,551
Federal share43%

of $956.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Aylmer
Construction start
Jul 9, 2018(actual)
Construction end
Aug 25, 2020(actual)

Against the original forecast

  • Construction start15 months lateforecast Apr 15, 2017
  • Construction end5 months lateforecast Mar 30, 2020

Also in Aylmer

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48501 in the federal list. How to read these figures.