Sewage Treatment Plant Upgrade - Northern

Prince Albert, Saskatchewan

completeWastewaterCC
Federal contribution
$734,166
Federal share29%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
20092010201120122013
Built
Program
Building Canada Fund - Communities Component
Construction start
May 9, 2011(actual)
Construction end
Mar 28, 2013(actual)

Against the original forecast

  • Construction start2 years lateforecast May 1, 2009
  • Construction end12 months earlyforecast Mar 31, 2014