Preservation of Rideau River Road

Smiths Falls, Ontario

completeHighways and RoadsCC
Federal contribution
$85,333
Federal share33%

of $256.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Montague
Construction start
May 14, 2009(actual)
Construction end
Jul 24, 2009(actual)

Against the original forecast

  • Construction end4 months earlyforecast Nov 30, 2009