Replacement of Leggetts Bridge

Burk's Falls, Ontario

completeHighways and RoadsCC
Federal contribution
$823,682
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Armour
Construction start
May 10, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jun 1, 2010
  • Construction end7 months lateforecast Mar 31, 2011

Also in Burk's Falls

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24705 in the federal list. How to read these figures.