Water System Improvements
Federal contribution
$496,879
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of the Village of Burks Falls
- Construction start
- Aug 8, 2016(actual)
- Construction end
- Oct 13, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2016
- Construction end3 months lateforecast Jun 30, 2017
Also in Burk's Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46208 in the federal list. How to read these figures.