Improvements to Burk's Falls Town Centre
Federal contribution
$150,000
Federal share100%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 25, 2009
ApprovedOct 27, 2009
2010
Built
Approved 4 months after the announcement.
- Program
- G8 Legacy Fund
- Ultimate recipient
- Municipality of the Village of Burks Falls
- Construction start
- Oct 27, 2009(actual)
- Construction end
- May 1, 2010(actual)