Improvements to Road 74 - London to Woodstock Link

Ingersoll, Ontario

completeHighways and RoadsCC
Federal contribution
$576,608
Federal share33%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Zorra
Construction start
May 26, 2009(actual)
Construction end
Dec 6, 2010(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Oct 29, 2010

Also in Ingersoll