Improvements to Road 74 - London to Woodstock Link
Federal contribution
$576,608
Federal share33%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Zorra
- Construction start
- May 26, 2009(actual)
- Construction end
- Dec 6, 2010(actual)
Against the original forecast
- Construction end5 weeks lateforecast Oct 29, 2010
Also in Ingersoll
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24759 in the federal list. How to read these figures.