King Street West Reconstruction
Federal contribution
$1.1M
$1,137,996
Federal share27%
of $4.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Ingersoll
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Oct 31, 2011(actual)