Reconstruction of Clark Road East - Ingersoll
Federal contribution
$1.5M
$1,515,124
Federal share33%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Ingersoll
- Construction start
- Oct 6, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Also in Ingersoll
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32530 in the federal list. How to read these figures.