Improvements to District Social Services Buildings

Parry Sound, Ontario

completeGreen EnergyCC
Federal contribution
$759,602
Federal share32%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Construction start
May 1, 2009(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 13, 2009
  • Construction end4 months earlyforecast Dec 31, 2010

Also in Parry Sound

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24767 in the federal list. How to read these figures.