Technology gateway experimentation and development
Federal contribution
$50,000
Federal share33%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 12, 2010
20092010
Built
Approved 16 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Trois-Rivières
- Construction start
- Jan 15, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24820 in the federal list. How to read these figures.