Schedule

Announced and approvedJan 30, 2009
200920102011
Built
Program
Building Canada Fund - Communities Component
Construction start
Jun 12, 2009(actual)
Construction end
Apr 26, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2009
  • Construction end2.9 years earlyforecast Mar 31, 2014