Municipal Water Treatment and Storage Improvements

Slave Lake, Alberta

completeDrinking WaterCC Top Up
Federal contribution
$2.9M
$2,937,774
Federal share31%

of $9.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Slave Lake
Construction start
May 10, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Mar 1, 2010
  • Construction end12 months lateforecast Nov 1, 2010