Kapaweno Adventure Trail

Slave Lake, Alberta

completeActive TransportationATF
Federal contribution
$500,000
Federal share99%

of $505.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2024
202320242025
Built

Approved 18 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Kapawe'no First Nation
Construction start
Mar 1, 2024(actual)
Construction end
Jan 12, 2025(actual)

Against the original forecast

  • Construction start18 months lateforecast Sep 1, 2022
  • Construction end21 months lateforecast Mar 31, 2023