Border to Beaches

Winnipeg, Manitoba

completeActive TransportationCC
Federal contribution
$1.5M
$1,453,204
Federal share33%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Construction start
Feb 22, 2010(actual)
Construction end
Dec 31, 2016(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jun 1, 2010
  • Construction end15 months lateforecast Sep 30, 2015