Border to Beaches
Federal contribution
$1.5M
$1,453,204
Federal share33%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Manitoba Recreational Trails Association
- Construction start
- Feb 22, 2010(actual)
- Construction end
- Dec 31, 2016(actual)
Against the original forecast
- Construction start3 months earlyforecast Jun 1, 2010
- Construction end15 months lateforecast Sep 30, 2015