Correction Line Road (TWP 470)
Federal contribution
$773,692
Federal share19%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20152016
Built
Approved 14 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Wetaskiwin No. 10
- Construction start
- Apr 1, 2015(actual)
- Construction end
- Sep 15, 2015(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Oct 31, 2015
Also in Wetaskiwin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24969 in the federal list. How to read these figures.