Correction Line Road (TWP 470)

Wetaskiwin, Alberta

completeHighways and RoadsCC
Federal contribution
$773,692
Federal share19%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20152016
Built

Approved 14 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Wetaskiwin No. 10
Construction start
Apr 1, 2015(actual)
Construction end
Sep 15, 2015(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Oct 31, 2015