Resurfacing Highway 13
Federal contribution
$1.7M
$1,727,785
Federal share50%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2010
- Construction end3 months earlyforecast Mar 31, 2011
Also in Wetaskiwin