Garden Meadows Reservoir

Wetaskiwin, Alberta

completeDrinking WaterCWWF
Federal contribution
$1.6M
$1,634,954
Federal share39%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Wetaskiwin No. 10 County
Construction start
Oct 10, 2017(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Oct 31, 2017
  • Construction end3 months lateforecast Sep 30, 2019