Back to projects

Beausejour Wastewater Collection & Treatment Betterment Program

Beausejour, Manitoba

completeWastewaterCC
Federal contribution
$158,333
Federal share33%

of $475.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Beausejour
Construction start
Mar 19, 2010(actual)
Construction end
Nov 29, 2011(actual)

Against the original forecast

  • Construction end4 months lateforecast Jul 31, 2011

Also in Beausejour