Beausejour Water Treatment Plant
Federal contribution
$5.0M
$4,956,000
Federal share40%
of $12.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2022
202220232024
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Beausejour
- Construction start
- Mar 29, 2023(actual)
- Construction end
- Oct 15, 2024(actual)
Against the original forecast
- Construction start5 weeks earlyforecast May 1, 2023
- Construction end8 weeks lateforecast Aug 23, 2024
Also in Beausejour
- Beausejour Lagoon Expansion and Chemical Treatment Addition$432.0K
- Beausejour Wastewater Collection & Treatment Betterment Program$158.3K
- Gillis quarry Active Transportation Trail$50.0K
- Town of Beausejour Active Transportation Plan - Phase 2$50.0K
- Brokenhead Trail Blazers Destination Trail Improvement$9.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62708 in the federal list. How to read these figures.