Town of Beausejour Active Transportation Plan - Phase 2
Federal contribution
$50,000
Federal share80%
of $62.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2023
20232024
Built
Approved 17 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Beausejour
- Construction start
- Mar 28, 2023(actual)
- Construction end
- Feb 8, 2024(actual)
Against the original forecast
- Construction start10 months lateforecast May 15, 2022
- Construction end3 months lateforecast Nov 15, 2023
Also in Beausejour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64545 in the federal list. How to read these figures.