Back to projects

Instrument Landing System - Brandon Municipal Airport

Brandon, Manitoba

completeRegional And Local AirportsCC Top Up
Federal contribution
$500,000
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Brandon
Construction start
Jun 14, 2010(actual)
Construction end
Jan 15, 2011(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Jan 31, 2011

Also in Brandon