Ile Des Chenes Lagoon Expansion
Federal contribution
$107,667
Federal share33%
of $323.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
201020112012201320142015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Ritchot
- Construction start
- Dec 21, 2014(actual)
- Construction end
- Sep 24, 2015(actual)
Against the original forecast
- Construction start8 months lateforecast May 1, 2014
- Construction end9 months lateforecast Dec 31, 2014
Also in St. Adolphe