Ile Des Chenes Lagoon Expansion

St. Adolphe, Manitoba

completeWastewaterCC
Federal contribution
$107,667
Federal share33%

of $323.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
201020112012201320142015
Built
Program
Building Canada Fund - Communities Component
Construction start
Dec 21, 2014(actual)
Construction end
Sep 24, 2015(actual)

Against the original forecast

  • Construction start8 months lateforecast May 1, 2014
  • Construction end9 months lateforecast Dec 31, 2014

Also in St. Adolphe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25316 in the federal list. How to read these figures.