St Adolphe East Dyke
Federal contribution
$2.2M
$2,161,074
Federal share31%
of $6.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
20092011201320152017
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Ritchot
- Construction start
- Jun 15, 2014(actual)
- Construction end
- Sep 30, 2017(actual)
Against the original forecast
- Construction end21 months lateforecast Dec 31, 2015
Also in St. Adolphe
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25524 in the federal list. How to read these figures.