St. Adolphe Pump Station Replacement

St. Adolphe, Manitoba

approvedDisaster MitigationGIS
Federal contribution
$3.6M
$3,650,000
Federal share50%

of $7.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2022
today
2022202420262028
BuiltForecast

Approved 12 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Province of Manitoba
Construction start
May 1, 2026(forecast)
Construction end
Oct 31, 2028(forecast)