Back to projects

Water Conservation Strategy - Water Meters

Raymond, Alberta

completeDrinking WaterCC
Federal contribution
$118,459
Federal share33%

of $355.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.6 years before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Raymond
Construction start
Jul 31, 2009(actual)
Construction end
Jul 20, 2010(actual)

Also in Raymond

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25683 in the federal list. How to read these figures.