Town of Raymond Wastewater Treatment System Expansion
Federal contribution
$3.2M
$3,200,000
Federal share40%
of $8.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 4, 2020
202120222023202420252026
BuiltForecast
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Raymond
- Construction start
- Nov 15, 2022(actual)
- Construction end
- Dec 15, 2025(forecast)