Highway 52 Improvements
Federal contribution
$156,862
Federal share50%
of $313.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJul 23, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- May 26, 2010(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2010
- Construction end5 months earlyforecast Mar 31, 2011
Also in Raymond
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36638 in the federal list. How to read these figures.