Back to projects

Pemberton Skate and Bike Skills Park

Pemberton, British Columbia

completeRecreationCC Top Up
Federal contribution
$122,618
Federal share33%

of $367.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Pemberton
Construction start
Nov 15, 2010(actual)
Construction end
May 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 15, 2010
  • Construction end5 months earlyforecast Oct 31, 2011

Also in Pemberton