Sunchild Road Base/Pave

Drayton Valley, Alberta

completeHighways and RoadsCC
Federal contribution
$2.2M
$2,208,900
Federal share33%

of $6.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Brazeau
Construction start
Jun 1, 2010(actual)
Construction end
Nov 15, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast Oct 1, 2009
  • Construction end5 months earlyforecast Mar 31, 2012