Back to projects

Town of Drayton Valley - Net Zero Aquatic Facility

Drayton Valley, Alberta

completeRecreationRNIS
Federal contribution
$7.6M
$7,584,956
Federal share40%

of $19.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 25, 2020
202120222023
Built

Approved 6 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Drayton Valley
Construction start
Apr 12, 2021(actual)
Construction end
Feb 5, 2023(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Apr 26, 2021
  • Construction end7 weeks lateforecast Dec 15, 2022

Also in Drayton Valley