Town of Drayton Valley South Sanitary Trunk Sewer Twinning

Drayton Valley, Alberta

completeWastewaterSCF
Federal contribution
$2.5M
$2,493,955
Federal share27%

of $9.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
201620172018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Drayton Valley
Construction start
Jun 2, 2019(actual)
Construction end
Dec 16, 2020(actual)

Against the original forecast

  • Construction start2.1 years lateforecast May 1, 2017
  • Construction end2 months lateforecast Oct 1, 2020