Creston Wastewater Treatment Plant Improvements - Cover, Secondary Clarifier and Backup Power
Federal contribution
$833,327
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
201020112012201320142015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Creston
- Construction start
- Sep 1, 2010(actual)
- Construction end
- Mar 31, 2015(actual)
Against the original forecast
- Construction start4 months earlyforecast Jan 1, 2011
Also in Creston
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26041 in the federal list. How to read these figures.