Creston Wastewater Treatment Plant Improvements - Cover, Secondary Clarifier and Backup Power

Creston, British Columbia

completeWastewaterCC
Federal contribution
$833,327
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
201020112012201320142015
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Creston
Construction start
Sep 1, 2010(actual)
Construction end
Mar 31, 2015(actual)

Against the original forecast

  • Construction start4 months earlyforecast Jan 1, 2011