Arrow Creek Water Main Replacement and System Improvements - Final Phase
Federal contribution
$2.5M
$2,507,417
Federal share50%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Central Kootenay
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Jun 1, 2018(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2017
- Construction end6 months earlyforecast Nov 30, 2018
Also in Creston
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47672 in the federal list. How to read these figures.