Arrow Creek Water Main Replacement and System Improvements - Final Phase

Creston, British Columbia

completeDrinking WaterCWWF
Federal contribution
$2.5M
$2,507,417
Federal share50%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 12, 2017(actual)
Construction end
Jun 1, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2017
  • Construction end6 months earlyforecast Nov 30, 2018