Creston - Kootenay River Dike Upgrades

Creston, British Columbia

completeDisaster MitigationCC
Federal contribution
$156,255
Federal share33%

of $477.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 9, 2010
20112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Reclamation Dyking District
Construction start
Feb 17, 2011(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction start8 months earlyforecast Nov 1, 2011