Squamish - Government Road Trunk Sewer Main
Federal contribution
$676,983
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- District of Squamish
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Mar 1, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 31, 2010
- Construction end4 weeks earlyforecast Mar 31, 2011
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Mamquam Wastewater Treatment Plant Upgrade$4.0M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough$2.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26147 in the federal list. How to read these figures.