Squamish - Government Road Trunk Sewer Main

Squamish, British Columbia

completeWastewaterCC Top Up
Federal contribution
$676,983
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
District of Squamish
Construction start
Jul 5, 2010(actual)
Construction end
Mar 1, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 31, 2010
  • Construction end4 weeks earlyforecast Mar 31, 2011

Also in Squamish

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26147 in the federal list. How to read these figures.