Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough
Federal contribution
$2.2M
$2,169,600
Federal share40%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2024
today
2024202620282030
BuiltForecast
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- District Municipality of Squamish
- Construction start
- Jun 25, 2025(actual)
- Construction end
- Dec 31, 2029(forecast)
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Mamquam Wastewater Treatment Plant Upgrade$4.0M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish - Jimmy Jimmy (Judd) Slough Culvert Replacement$1.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67752 in the federal list. How to read these figures.